Dulles Corridor Metrorail
Project Update
Current Status.
The most recent steps that have been taken regarding the Dulles
Corridor Metrorail project are captured in correspondence between
Federal Transit Administrator James S. Simpson and Governor Timothy
M. Kaine and from James E. Bennett, President and Chief Executive
Officer (CEO) of the Metropolitan Washington Airports Authority (MWAA),
and Administrator Simpson in letters dated January 24, 2008, and
February 1, 2008. (View correspondence here.)
In his January 24,
2008 letter, Federal Transit Administrator (FTA) Simpson outlined a
number of concerns that FTA had with the Dulles Corridor Metrorail
project. These include: "(1) the management arrangements under
which the Project would be implemented; (2) MWAA's limited
experience with transit projects and with exceptionally large
design-build contracts; and (3) the uncertainties of the Washington
Metropolitan Area Transit Authority's (WMATA) ability to finance its
ongoing capital needs systemwide in order to maintain service levels
and a state of good repair."
During the summer
months of 2007, the Dulles Metrorail project was reviewed by Project
Management Oversight Consultants for FTA, a necessary step before
receiving approval to enter the Final Design of Phase 1. The
project team had hoped to receive t this approval before the end of
the year. In late summer, FTA warned that the project was having
trouble meeting its cost-benefit criterion. To respond to this
concern, the project team submitted a list of proposed cuts of
totaling $300 million to FTA in a letter dated September 24, it
2007. Subsequently, $242 million of these proposed cost adjustments
were accepted by FTA. As recently as November, Jim Bennett reported
at the Annual Meeting of the Dulles Corridor Rail Association, that
FTA and the project team staff had been working well together and it
seemed that they had reached agreement on the cost of the project.
As Governor Kaine
noted in his February 1, 2008, letter, the project team had begun to
hear external reports that FTA had other concerns but could get no
confirmation of these new issues until the Governor met with US
Secretary of Transportation Mary Peters and Administrator Simpson on
January 24. These concerns were put in writing in a letter dated
January 24, 2008, from Administrator Simpson to Governor Tim Kai of
ne.
Senator John Warner
asked Secretary Peters for a brief "cooling off" period during which
the state and the Airports Authority could respond to the issues
raised by FTA. As reported in the Washington Post (January 29,
2008, Amy Gardner) Warner said that Secretary Peters would work with
Governor Kaine to try to resolve differences over the cost and
management of the proposed 23-mile Metrorail extension.
In his February 1,
2008, letter, Governor Kaine said that he hoped his response to the
issues raised by FTA would be the basis of a dialogue with federal
transportation officials. "We want to fully understand your
concerns and then look creatively at how to resolve them to allow
the project to continue forward. Your willingness to entertain this
dialogue prior to rendering in a final determination on the project
is most appreciated." Kaine wrote that the project contractor has
agreed to mitigate price and schedule impacts for at least 30 days
to allow the opportunity for dialogue. He wrote, "Simply put, the
unshakable goal of the combined Virginia congressional delegation,
and all state, local and private partners is to make this project
work and to do so in partnership with the federal government."
Project History
1964 The
Federal Aviation Administration's master plan for Dulles
international Airport recommends a transit line along the Dulles
Airport Access Road.
1990 The
Virginia Commonwealth Transportation Board adopts a program for the
Dulles corridor that includes rail service.
1994 Virginia
and Metro officials initiate a Major Investment Study (MIS) to
evaluate transit options for the corridor
1996 The MIS
says that Metro-like heavy rail would be the best transit option to
the Dulles Airport.
1999 FTA
approves the 1999 Transportation Planning Board (TPB) Constrained
Long-Range Plan, including the ability to construct Dulles extension
and operate/maintain the total Metrorail system.
2000 FTA
Approves Initiation of the Environmental Impact Statement (EIS)
2002 The
Fairfax County and Loudoun County Board of Supervisors, WMATA, and
state officials endorse a mostly above ground route through Tysons
as the Locally Preferred Alternative
2002 FTA
advises Virginia that funding limitations require a phased approach
and a revised EIS
2003 FTA
approves a supplemental draft EIS for the two-phase project
2004 FTA
approves Preliminary Engineering for Phase 1 of Dulles rail.
Fairfax County begins collecting a real estate tax from commercial
landowners in the Phase 1 tax district (Tysons Corner area and along
the Dulles corridor to Wiehle Avenue in Reston) to pay for the rail
line
2004 FTA
approves Dulles Transit Partners contract (PPTA) as meeting federal
competitive procurement requirements
2005 Virginia
imposes toll increases on the Dulles Toll Road to help finance the
rail project (May 22, 2005)
2005 FTA rates
the project as "recommended" in the FY 06 New Starts Report
2006 FTA
approves an amended EIS Record of Decision
2006 FTA
approves MWAA as having the "financial, legal and technical capacity
to lead the Dulles rail project"
On January 26,
2007, Administrator Simpson wrote to the Virginia congressional
delegation that "the only significant outstanding issue at this time
is whether or not the project's estimated cost would comply with the
new starts criteria."
Issues Raised by
the Federal Transit Administration (Simpson letter to Governor Kaine,
January 24, 2008) Responses from Governor Kaine and Airports
Authority President Jim Bennett in letters dated February 1, 2008
Cost Effectiveness. Both Kaine and Bennett note the FTA accepted $242
million of proposed reductions, which reduced the overall project
cost to $2.55 billion ($2.96 billion including financing). Kaine
requests that the FTA acknowledge that this reduction would place
the cost effectiveness of the Dulles rail project within the
required range.
Capital Financial
Plan.
The January 24, 2008, FTA letter raises concerns about the capital
financial plan, which include (1) optimistic assumptions about the
number of toll transactions on the Dulles Toll Road and the growth
in toll revenues; (2) an aggressive financing structure which
includes significant back loading of debt; and (3) significant
growth in capital rehabilitation and replacement costs for the WMATA
system. All of which would result in a rating for the capital
financial plan of "Medium-Low."
Bennett notes in
his letter of February 1, 2008, that the size of the anticipated
TIFIA loan has been decreased and the size of the Dulles Toll Road
revenue bonds has been increased by approximately $70 million. This
increases the percentage of funds that can be considered committed
local funding for the project to over 75 percent, which would meet
the threshold for a “Medium High” rating in the subcategory of
Commitment of Capital Funds.
Bennett also notes
that the forecast Dulles Toll Road transactions have been updated to
reflect the actual toll revenues and the base case has been modified
to reflect an annual growth in toll transactions of 0.4%, a
conservative forecast that shows revenues from the toll road are
adequate to finance the local share of the project.
To address FTA
concerns about debt, Bennett notes the team has restructured debt
repayment assumptions to reduce the amortization in later years.
The operating plan has been updated with new information to address
FTA's concerns with WMATA’s operating conditions. Based on WMATA’s
strong commitment of operating funds and its financial commitment
and reasonable planning assumptions, Bennett states the Operating
Financial Plan should be eligible for a “Medium” rating.
Capacity of the
Airports Authority and Project Management Team to Manage the Project
The Airports
Authority’s responded to concerns about its capacity by providing
the professional qualifications of the consolidated project
management team and materials showing the integration of the team
with WMATA, Fairfax County and other project partners. It also
provided a description of its $7.2 billion capital construction
program, which includes a $1.3 billion automated fixed guideway
system. Bennett's letter notes that the materials provided to FTA
demonstrate that the Airports Authority has the legal, financial,
and technical capacity to manage the project. He notes that the
Project Management Oversight Consultant technical review reaches the
very same conclusion subject to the addition of certain personnel,
which is currently being addressed by recruitment efforts.
Concerns with the
Airports Authority's working Relationship with WMATA.
Bennett notes that the January 31, 2008, letter from John Catoe,
WMATA General Manager, expresses and reaffirms Metro's strong
support for the Dulles Corridor Metrorail project. Catoe notes an
FTA reference to correspondence about staff to staff communications
was about routine technical issues and did not rise to a significant
level. Catoe expressed his commitment to working to resolve issues
consistent with the approved intergovernmental agreement and
supporting Metro Board resolutions.
Project
Design-Build Contract
Bennett’s February
1 letter states that Dulles Transit Partners (DTP) has assumed the
risk of completing the majority of the project for the firm
fixed-price of $1.1 billion of the $1.6 million contract, thus
addressing FTA concerns about unrestrained cost escalations and
costly schedule delays. Approximately $500 million of allowances
are not included in the fixed-price contract to provide for a
competitive, transparent procurement environment once the design for
such items is sufficiently developed to enable subcontractors to bid
on the work. Bennett notes that the possibility of additional
payments to DTP is limited and would require substantial documentary
evidence. Also, DTP has assumed full responsibility for all design
and integration efforts between preliminary and final engineering.
That eliminates a major risk of using a design and build delivery
system.
Ability of WMTA to
Finance its System-wide Capital and Operating Needs and to Maintain
the Project in a State of Good Repair.
Bennett notes that
the WMATA Board of Directors has determined that the Authority will
be financially capable of operating maintain the project. It voted
to approve the financial plan for the project on June 24, 2007. It
found that the cost of operating and maintaining Phase 1 is within
the financial capacity of WMATA and contributing jurisdictions. The
project will represent less than 4 percent of the Capital
Improvement Program for 2008-2013. WMATA member jurisdictions have
made a commitment to long-term rehabilitation and replacement needs
through the Constrained Long-Range Plan which demonstrates estimated
revenues that can reasonably be expected to be available equal the
estimated costs of expanding while adequately maintaining and
operating the transit system from 2007 through 2030.
Both the
Commonwealth and the Airports Authority recognize that a regional
strategy is needed to address WMATA's long-term capital needs.
Substantial progress has been made
The three member
jurisdictions-Virginia, Washington, DC, and Maryland have taken
steps to secure stable and dependable long-term funding for the
re-capitalization of the Metro system. In 2007, the Virginia
General Assembly approved a transportation funding bill that could
include up to $500 million for transportation projects in Northern
Virginia of which $50 million would be dedicated to WMATA off the
top. On April 27, 2006, Mayor Anthony Williams signed a bill to
dedicate one half of 1 percent of the DC retail sales tax to provide
additional funding for maintaining and improving Metro. In 2007,
the Maryland General Assembly provided dedicated funding for WMATA
through the State’s transportation trust fund. As Bennett notes in
his letter, these funding sources, along with the passage of Federal
legislation, would provide a steady stream of funding for WMATA’s
long-term capital needs.
In concluding
his letter, Bennett says that he believes the project qualifies for
an overall "Medium" rating. Both he and the Governor call for
working through any remaining issues with the hope that a continuing
dialogue among all parties will enable this important regional
transit project to move forward.
In addition to
Administrator Simpson's letter of January 24, 2008 and the
responding letters of Governor Timothy Kaine and James E. Bennett,
President and Chief Executive Officer, MWAA, a number of other
letters have been sent in support of the project by: Governors
Timothy Kaine (Virginia) and Martin O’Malley (Maryland) and Mayor
Adrian M. Fenty to US DOT Secretary Mary Peters and FTA
Administrator Simpson; John B. Catoe, Jr., General Manager, WMATA
to James E. Bennett, MWAA; the Northern Virginia Congressional
Delegation to Administrator Simpson; Members of the General Assembly
To Administrator Simpson; Gerald E. Connolly, Chairman, Fairfax
County Board of Supervisors to Administrator Simpson; Loudoun County
Board of Supervisors Chairman Scott York transmitting a resolution
passed by the Loudoun County Board; letter from Robert F. McDonnell,
Attorney General, Commonwealth of Virginia to Secretary Peters and
Administrator Simpson. These letters can be found by clicking
here. (View correspondence)
Public Support
and Outreach Activities.
In late October 2007, The Dulles Corridor Rail Association
commissioned a survey that indicated 93 percent of Northern
Virginians and 87 percent of residents regionwide support the Dulles
Metrorail project. (View
survey here.)
Building on the
survey, DCRA placed two full-page ads in the Washington Post on
January 10 and January 29, 2008, and one in the Washington Examiner
on January 16. The January 29th ad was in the form of a
letter to President George w. Bush asking for his support. The
Greater Washington Board of Trade and the Washington Airports Task
Force signed onto both ads, which also included a list of businesses
and groups supporting Dulles Metrorail Now!
The Letter to
President Bush ads was also placed in the Washington Times on
February 1 the date of a press conference organized by the Dulles
Regional Chamber. Other business groups that participated in the
press conference included the Loudoun County, Fairfax County, and
Greater Reston Chambers of Commerce, the Greater Washington Board of
Trade, the Dulles Area Transportation Association, the Dulles
Corridor Rail Association, the Committee for Dulles, and the
Washington Airports Task Force. The press conference, highlighted
the different positive impacts that rail will have on large and
small businesses, hospitals, and nonprofits, employees, and
individuals and the problems businesses have now because of a lack
of reliable rail transit in the Dulles corridor.
The businesses
groups are cooperating on an extensive communications campaign the
purpose of which is to demonstrate to the Secretary Peters,
Administrator Simpson, President George W. Bush and members of the
Bush Administration the tremendous support for the Dulles Metrorail
project. The campaign has involved writing letters, sending faxes,
and making phone calls to key officials.
Special thanks
go to the Northern Virginia Congressional delegation, which includes
Senator John Warner and Congressman Frank Wolf, long-time supporters
of rail in the Dulles corridor and Senator Webb and Congressmen Tom
Davis and Jim Moran. They are working tireless on our behalf to
facilitate reaching agreement on project issues so that this
critical regional project can move forward. Please thank them for
their efforts.
Sign on in
support of Dulles Metrorail Now!
Supporters of rail have a created the Dulles Metrorail Now! advocacy
group. Visit
www.DullesMetrorailnow.org to sign up in support of the Dulles
Metrorail project and to receive project updates.
Project Receives Major
Approvals. The Dulles Corridor Metrorail Project
gained significant momentum during the month of June 2007. The
Fairfax and Loudoun County Boards of Supervisors approved
intergovernmental and local funding agreements on June 18
and 19 respectively. On June 28, 2007, the Board of
Directors of the Washington Metropolitan Area Transit
Authority (WMATA) approved an Intergovernmental Agreement
with the Metropolitan Washington Airports Authority (MWAA)
and a Financial Plan for a Full Funding Grant Agreement
including Metro’s Financial Capacity.
The Fairfax County Board of Supervisors
received a presentation on the project at a public meeting on June 4.
Two weeks later, on June 18, the board voted to:
-
Authorize the County Executive to execute
a Local Funding Agreement with the Metropolitan Washington Airports
Authority (MWAA) for the construction of Phase 1 of the Dulles
Corridor Metrorail Project subject to the following conditions:
-
That the project scope remains as
defined in the agreement approved on June 6, 2007, between WMAA and
Dulles Transit Partners and that no alterations or modifications are
made to the project scope without prior approval of the Board.
-
That the project receives a risk
assessment rating satisfactory to the Federal Transit Administration
(FTA).
-
That the total project cost accompanying
the request for a Full Funding Grant Agreement not exceed $2.647
billion
-
That the Local Funding Agreement be
executed as part of the request to FTA for a Full Funding Grant
Agreement
-
Authorized the County Executive to execute
a Cooperative Agreement between Fairfax County and MWAA which defines
the policies and procedures that will be used to design, review, and
approve Phases 1 and 2 of the Dulles Corridor Metrorail Project,
subject to the Commonwealth of Virginia’s continuing role in the
project following the transfer of the project to MWAA.
-
Authorize the County Executive to expend
funds from the Dulles Rail Phase 1 Special Improvement Transportation
District in accordance with the terms of the petition of the tax
district and in accordance with the cash-flow requirements of the
project, and to establish a buy-out procedure for commercial and
industrial properties that may in the future be converted to
residential use.
On June 19, 2007, the Loudoun County Board
of Supervisors authorized its County Administrator to sign A Memorandum
of Understanding entering the County into a three-party Funding
Agreement with Loudoun, Fairfax and the Metropolitan Washington Airports
Authority for the purpose of constructing Metrorail to Loudoun County.
On June 28, the Washington Metropolitan Area
Transit Authority approved a resolution authorizing the General Manager
to execute the Intergovernmental Agreement with MWAA, increase the
on-call consultant work program by $250,000 and increase the FY 2008
through 2012 WMATA budget by $272,850,000.
The resolution also indicated that the Board
of Directors acceptance and approval of the Intergovernmental Agreement
was contingent on the scope of the project as defined and any future
changes to this project scope would require reconsideration and further
approval by the WMATA Board
The WMATA Board also adopted a Financial
Plan for Full Funding Grant Agreement Including Metro's Financial
Capacity. This resolution affirmed that the cost of operating and
maintaining WMATA's current bus and rail systems, in addition to Dulles
Phase 1, is within the financial capacity of WMATA and the contributing
jurisdictions and approved the final operating financial plan.
The state has requested FTA approval to
enter Final Design for Phase 1 and to obtain a Full Funding Grant
Agreement. Property acquisition has begun and utility relocations are
expected to begin in September 2007. If the FTA approves the FFGA by
the end of February 2008 as anticipated, construction could begin in the
first quarter of 2008. Rail passenger service is expected to begin in
2013, with the Phase 2 extension coming online in 2015/2016.
The Local Funding Agreement between MWAA and
each funding partner includes:
-
Funding commitment (share)
-
Cost reductions and increases
-
Shared betterments
-
Individual betterments
-
Timing of contributions
-
Concurrent Non-Project Activities (CNPA)
-
Congestion Management Plan (CMP)
Project
Schedule – Phase 2
Phase 2 construction anticipated prior to
Phase 1 operations
Phase 2 rail operations – 2015/2016
Road work will start on widening Route 7 in
the spring of 2008 as one of the first items of construction. The
three-lane in each direction configuration will be widened to four-lanes
with the addition of a right turn lane in each direction. The widened
street will include a landscape strip for tree plantings and sidewalks
ranging from eight to 11 feet in width, which will be widened to 25-30
feet when adjacent properties are redeveloped. The service roads will
be eliminated and there will be dual left- turn lanes at the existing
intersections. Mid -block left-turn lanes will be eliminated.
Pedestrian crossings will be added. Pedestrians will also be able to
cross the street at the Metrorail stations using elevated access
walkways.
Transportation Management Planning, The Department of Rail and Public Transportation, MWAA, and the Virginia
Department of Transportation are developing a Congestion Mitigation Plan
which consists of two elements: Maintenance of Traffic (MOT) plan and a
Transportation Management Program (TMP).
The goals of the MOT plan are to help
travelers move through the construction area, sustain economic activity,
and ensure safety for commuters, shoppers, and construction workers.
The TMP plan will try to reduce the number of single occupant vehicles
in Tysons Corner. It will focus on strategies in a number of areas
including: public/business outreach, communication tools to enable
people to make informed decisions before and during their travel,
improving incident response and management, enhancing ridesharing
(transit, vanpool, carpool and carsharing) and telecommuting options,
encouraging employer sponsored activities (Alternate work schedules,
commuter assistance programs, preferential parking) and making minor
roadway improvements to facilitate traffic movement within the affected
area.
A comprehensive transportation management
plan is also being developed for Northern Virginia to coordinate the
congestion management efforts of several major projects anticipated to
be under construction in northern Virginia during the same time
including besides Dulles Metrorail, HOT lanes on the Capital Beltway and
HOT lanes on I-395/I-95.
MWAA Management of Dulles Toll Road
The Commonwealth and MWAA have agreed to a
50-year Transfer Agreement which requires that MWAA:
-
Operate, maintain, and improve the Dulles
Toll Road
-
Manage construction of the Metrorail
extension
-
Finance all debt service for the Metrorail
project and Toll Road improvements
The transfer agreement requires local
funding agreements for the Metrorail extension and intergovernmental
agreements with the project partners. These approvals were provided by
Fairfax and Loudoun counties and the WMATA board in June. The agreement
also requires the issuance of final design approval by the FTA.
Distribution of Phase 1 Project Cost
-
FTA "New
Starts" $0.900 billion
-
State
contribution $0.051 billion
-
Fairfax County
$0.400 billion
-
Dulles Toll Road
$1.296 billion
-
Phase 1 Project Cost $2.647
billion
Dulles Rail Total Funding Requirements (from MWAA presentation)
-
Phase 1 and 2 combined cost estimated at
$5.147 billion
-
Commonwealth: Capped at $75 million
-
Federal “New Starts”: Capped at $900
million
-
MWAA (airport revenues): $211 million or
4.1% of final costs
-
Loudoun: $247 million or 4.8% of final
costs
-
Fairfax: $829 million or 16.1% of final
costs
-
Dulles Toll Road: $2.85 billion 56% of the
total cost
Dulles Toll Road Rates (from MWAA
presentation)
2007- Average toll: $.60
2010 - Average toll: $.85 (Increase
pre-approved by Commonwealth Transportation Board in 2005)
2013 - Average toll: $1.10 (Present value
average toll: $.90)
2016 - Average toll: $1.35 (Present value
average toll: $1.01)
2025* - Average toll: $1.83 (Present
value average toll: $1.04)
2035* - Average toll: $2.47 (Present
value average toll: $1.05)
*2025 and 2035 toll increases would fund
operation and maintenance keeping up with inflation. Rail
improvements would have been paid for
MWAA will engineer the Dulles Toll Road to
improve flow, increase usage of E-ZPass, implement new generation toll
collection systems, improve ingress and egress ramps to increase usage
of the road and enforce violations.
The funding partners will work together to
find other project funding sources including: private funding of parking
garages, Federal Highway Grants, and Transportation Security
Administration Grants.
FTA Actions. On May 23, 2007, Scott
A. Biehl, Deputy Chief Counsel, FTA, wrote to Peter M. Rosen, Akin Gump
Strauss Hauer and Feld LLP to deny the Tysons Tunnel Incorporated
petition requesting among other things that FTA reopen the environmental
review process for the Dulles Corridor Metrorail Project. Notice of
this action appeared in the Federal Register of May 30, 2007, pp. 30049
and 30050 “Notice of Limitation on Claims against a Proposed Public
Transportation Project”.
At the same time, FTA made public a report
it had prepared by Hill International, Inc. titled “Review of DRPT
Evaluation of Tysons Tunnel, Inc. Proposal for Large Bore Tunnel, Spot
Report - Final May 15, 2007”. This report evaluated the conclusion of
the Carter & Burgess report prepared for DRPT on the Tysons tunnel
proposal.
It states, “The construction of a Large Bore
Tunnel using and EPB boring machine, while it may be technically
feasible in concept, has not been sufficien6ly investigated to be able
to proceed with an acceptable level of confidence in project
completion. There has been no detailed subsurface investigation
suitable to support the TTI conclusions with respect to tunnel advance
rate or construction cost. The degree of difficulty of successfully
completing the project as proposed by TTI is vastly understated.”
Design-Build Agreement for Phase 1. On March 30, 2007, the Virginia Department of Rail and Public
Transportation (DRPT) announced the successful negotiation of a $1.6
billion design-build agreement with Dulles Transit Partners, LLC for
final design and construction of Phase 1 of the Dulles Corridor
Metrorail Project. The agreement shares project risk with Dulles
Transit Partners.
-
The final contract document and additional
details is available on the MWAA web site at www.mwaa.com.
-
Total project price for Phase 1 is $2.4 to
$2.7 billion, which is expected to keep the project eligible for $900
million in federal funds by meeting FTA's requirement for
cost-effectiveness
-
Approximately $1.1 billion of the
Design-Build Agreement (55 percent) is a fixed price element
including critical components to be performed directly by Dulles
Transit Partners such as construction of the aerial structure and
approximately 2,100 foot long tunnel in Tysons Corner
-
The remaining $500 million (45 percent) is
for competitively procured subcontractors and competitively procured
materials and equipment., such as electrical power systems and station
finishes that will be open to competition later in the construction
process
-
This allows for market pricing for
elements to be built several years into the construction schedule.
-
Price includes $128 million of utility
relocation work to be performed by Dulles Transit Partners in the fall
2007 to be completed before the holiday season.
Process. The current agreement
builds on more than a decade of planning, environmental review and
engineering for the extension of Metrorail to the Dulles corridor. The
Federal Transit Administration has been a part of the process and
prepared the final Record of Decision, which was amended in November
2006. FTA has said that the state were to consider another alternative
it would have to start the federal process all over again.
There significant competition for a very
limited amount of federal funds for New Starts only $1.5 billion is
appropriated annually to the new starts program. More than 300 projects
are authorized for New Starts funding.
In the summer 2006, at the request of
Fairfax County, Secretary of Transportation Pierce Homer asked the
American Society of Civil Engineers to analyze the use of a large-bore
tunnel under Tysons Corner. After meeting with federal officials, on
September 6, 2006, Governor Tim Kaine decided to move forward with the
aerial/partial tunnel alternative rather than risk the loss of federal
funding.
Virginia's Public-Private Partnership Act
of 1995. As a result of a major investment study performed in the
mid-19 90s, the Commonwealth Transportation Board approved Metro like
rail for the Dulles corridor. In 1995, the Washington Metropolitan Area
Transit Authority made the decision to no longer do rail extensions as a
regional projects paid for by the entire region. Future extensions would
be paid for by the jurisdictions in which it was running. During
Governor Gilmore's administration, the PPTA was approved. It was
thought to be an appropriate vehicle to share the risks of the Dulles
Metrorail project. The state reached agreement with Dulles Transit
Partners to undertake the preliminary engineering of Dulles Metrorail
project. The PPTA process takes advantage of risk sharing mechanisms
and provides schedule and cost savings. This is the first transit
project to be advanced under the PPTA. |